How to maximize utilization of catalyst in commercial-scale fixed-bed reactor.

On this Page :

The important point frequently received from customers, when new or existing reactor designed, reconfigured, or replaced with new catalysts, is how to totally use catalyst performance during operation.

Scienifically, the catalyst performance in commercial-scale reactor depends on what rate-limiting step controls the overall reaction rate.

No alt text provided for this image

From the figure, the rate of film diffusion from bulk fluid to catalyst surface is slowest step and the overall rate of reaction is controlled by external mass transfer. In this regime, reactants are rapidly converted to products as fast as they arrive at the external surface of the catalyst. Consequently, the concentration of reactants is near zero at external interface of the catalyst and bulk fluid that it means poor utilization of catalyst. In other words, practically, chemical reaction engineer may “avoid” to design reactor operated in film-diffusion limitation.

The efficiency should be over 95% that it means the resistance due to film diffusion being less than 5% of the resistance due to chemical reaction. The main parameters influencing the efficiency may be included:

  1. Catalyst activity and its severity
  2. Nature of main reaction
  3. Phase & concentration of main reactant
  4. Flow behavior
  5. Catalyst shape and size

Recommedation

  • Use high velocity of fluid through catalyst bed
  • Improve flow distribution in order to maximize catalyst wetting efficiency
  • Achieve Plug flow behavior (see in https://www.linkedin.com/pulse/why-ideal-flow-pattern-crucial-upscaling-ixed-bed-reactor-sungnoen/?trackingId=MulVhhtlSACq%2F9cTpLL%2BuA%3D%3D)
  • Increase geometric surface area of catalyst

‍

Connect with our
Competency
Connect
featured insights
Process Scale-Up
Article
Bridging the Gap – Understand a Key Differences Between a Small Beakers to Larger Sizes.
The journey from a laboratory experiment to a commercially viable process is challenging step i.....
OSVARD
Process Scale-Up
Article
Bridging the Gap – Understand a Key Differences Between a Small Beakers to Larger Sizes.
The journey from a laboratory experiment to a commercially viable process is challenging step i.....
OSVARD
Engineering Design
Article
Why is Ideal flow pattern crucial for upscaling Fixed-bed reactor ?
The challenge in fixed-bed reactor scale up is partial similarity of laboratory, pilot, and commerci
OSVARD
Process Scale-Up
Article
Strategies for Reducing Cost and Schedules in Pilot Plants
Reducing capital costs and schedules in pilot and demonstration plants is crucial for the succe.....
OSVARD
Chemical Technology Development
Article
10 Common belief but False Idea on Net Zero Emission
People often interpret "Net Zero" as an end state where no emissions are being produced at all. This
OSVARD
Process Scale-Up
Article
What are Main Differences between Lab, Pilot, Demonstration and Commercial Plant in A Nutshell ?
Nowadays, many companies have been constantly transforming from production-and operation-based compa
OSVARD
Chemical Technology Development
Article
The Key Concern with Biofuels
Biofuels like ethanol and biodiesel have been getting a lot of attention. Ethanol is often mixed....
OSVARD
Chemical Technology Development
Article
A Practical Guide to Create a Reasonable Marketing Plan for Chemical Technologies
For natural scientists and engineers, it sometimes might be difficult to become with marketing, ....
OSVARD
Engineering Design
Article
Unraveling the Mystery of Catalyst Deactivation: The Hidden Challenges in Catalyst Development
Catalyst deactivation, the process whereby a catalyst loses its catalytic activity and/or select....
OSVARD
Simulation and Digitalization
Article
Scaling the CCS: What are Technical Challenges ?
Carbon Capture and Storage (CCS) is a technology for reducing carbon dioxide (CO2) from various emii
OSVARD
Safety Engineering
Article
Ensuring isothermality is important in lab and pilot-scale tests.
In catalyst development, laboratory and pilot plant are generally used for producing reliable inform
OSVARD
Simulation and Digitalization
Article
Understanding about “Levelized Cost of Energy (LCOE): What should we know, what should we do?
Accelerating decarbonization has been focused on our world. Numerous companies deploy their ambition
OSVARD
Engineering Design
Article
How to maximize utilization of catalyst in commercial-scale fixed-bed reactor.
The important point frequently received from customers, when new or existing reactor designed, recon